Entegre Prefabrik Pompa İstasyonu

ÜRÜNE GENEL BAKIŞ

Entegre Prefabrik Pompa İstasyonu

Fabrika entegreli GRP şaft, dalgıç pompalar, boru hatları, vanalar, seviye sensörleri, kontroller ve havalandırma; yerçekimi akışının olmadığı drenaj ve kanalizasyon kaldırma işlemleri için.

KEY SPECIFICATIONS

Equipment Series
YHWT(A) Integrated Prefabricated Pump Station
Shaft Material
Computer-controlled filament-wound GRP (fibreglass); uniform wall thickness meeting design requirements
Integrated Components
Submersible pumps, automatic coupling + guide rails, pipes, valves, level sensors, control panel, grille / basket screen, ventilation
Model Format
YHWT(A) + number of pumps / head (m) / flow (m³/h) / single-pump power (kW) / collection-shaft volume (m³)
Installation
Fully buried where included in the agreed site scope; access hatch and control box above ground
Operation & Control
Automatic start/stop by liquid level; alternation, alarms and remote monitoring confirmed per project
Maintenance
Pumps on guide rails with automatic couplings; sump and maintenance access confirmed per project
Media & Use
Domestic sewage, rainwater and general drainage lifting
Power Supply
380 V / 50 Hz (per project configuration)
Quality
Assembly, inspection and documentation scope confirmed in the quotation

ÜRÜN AVANTAJLARI

Mühendislik Avantajları

A factory-built sewage and drainage lifting station that replaces conventional concrete wet-wells on sites where the depth needed to be below the gravity network.
01

Filament-wound GRP shaft, uniform wall thickness

The shaft is made by a computer-controlled filament-winding process. Material, wall design and structural requirements are confirmed against the installation conditions.

Computer-controlled filament winding, design-uniform wall
02

Fully buried installation with low site impact

The collection shaft is installed below ground, with access, ventilation and the control interface arranged for the selected site layout.

Fully buried; hatch + control box only above ground
03

One-piece factory integration and pre-testing

Pumps, guide rails, internal pipes, valves, level instruments, screening and controls are coordinated as one equipment package. The quotation defines assembly and inspection scope.

Factory integration and testing where included in the agreed scope
04

Base and guide-rail coupling configured for easier maintenance

Automatic couplings and guide rails support pump removal through the access opening. Sump geometry and maintenance arrangements are confirmed in the project design.

Automatic coupling and guide-rail arrangement
05

PLC level control, unattended operation

Level signals provide automatic pump start and stop. Pump alternation, standby response, alarms and logging are included where identified in the agreed control schedule.

Project-defined level control and alarm logic
06

IoT remote monitoring ready

Remote communications and monitoring can be evaluated as optional functions after the required signals, protocol and operator interface are defined.

Optional; confirm protocol and monitoring scope

UYGULAMA SENARYOLARI

Nerede Çalışır

Belediye Drenajı
01

Belediye Drenajı

Alçak alanlar, yollar, parklar ve şebekeler için yağmur suyu ve kanalizasyon toplama ve kaldırma.

Binalar ve Endüstriyel Parklar
02

Binalar ve Endüstriyel Parklar

Konut, ticari ve endüstriyel gelişmeler için kompakt drenaj altyapısı.

Residential and Commercial Sites
03

Residential and Commercial Sites

Buried collection and lifting for developments with limited plant-room space.

Industrial Park Drainage
04

Industrial Park Drainage

Project-selected lifting for compatible drainage and wastewater collection duties.

PROJE DESTEĞİ

Parametrelere, seçime veya özel bir yapılandırmaya mı ihtiyacınız var?

Çalışma koşullarınızı paylaşın, mühendislik ekibimiz takip edecektir.
Yuanheng ile İletişime Geçin →